Welcome To
Summer Breeze
A Lake Front Community Located on
Beautiful Norris Lake
Home
Vacation Rentals
For Sale
Links and Articles
Contact Us
75-
Source: Knoxville News Sentinel Co.
SHARPS CHAPEL -
"This is not a typical bridge job," said Duane Manning, Tennessee Department of Transportation assistant regional construction supervisor.
"This bridge has the deepest foundation of almost any bridge in Tennessee, but certainly in East Tennessee.
"You can't see what you're doing. It's like arthroscopic bridge building. Everything is done from above. You can't send someone down to the bottom to see what you're doing," Manning said.
Since Nov. 4, 2009, crews with Mountain States Contractors have been working on the structure, which at $22.4 million is the second most expensive bridge project in progress in East Tennessee, Manning said. The Henley Bridge in Knoxville, at $24.7 million, is more costly.
Work was temporarily halted at Norris last week after the death in Knoxville of a worker on the Henley Bridge renovation. A safety review of all projects under Britton Bridge LLC and its affiliates, including Mountain States Contractors, is under way.
TDOT expects the safety review to take about a week.
For those in Union County, replacing the 75-
"It'll be good for the community and a lot safer for drivers," said Matthew Boss, a bartender at the Bubba Brews Sports Pub and Grill that's within sight of the project.
"It should have been done 10 years ago. Every time it rains it floods."
The slogging pace of work on the new bridge -
"We've heard more rumors on this bridge than any project," Manning said. "It's not funded, the company has folded, the old bridge is falling down; all kinds of stuff.
"It's a small community, so people talk. But we're fully funded from start to finish. There are no major hiccups thus far."
The new bridge is slated to be carrying traffic and the old structure dismantled
by June 30, 2012. Although 19 months have passed on the 32-
"Without an approved extension, he (the contractor) could be looking at liquidated damages of $2,100 per day if he goes past the June 30, 2012, date," Manning said.
Manning said the contractor has not requested a time extension.
Pouring concrete
Workers so far have erected two sets of support pillars for the new bridge. Each
pillar is 10 feet in diameter. They have four more sets of supports to construct.
Each of those pillars sits upon a 32-
"Footings are the most important part of it all," said James P. Braden Jr., a TDOT project supervisor with 42 years of experience. "If it moves, you've got trouble."
Workers on barges position a metal frame called a cofferdam on the floor of the river
and install sheet pilings more than 70 feet high to drain as much water as possible
from the area. Drills on the barges dig 15-
Bill Malone, TDOT operations specialist 2 with 42 years of experience, said each pillar consists of up to 2,000 cubic yards of concrete and 250,000 pounds of metal rebar more than an inch in diameter.
Because the new bridge is within 40 feet of the old Veterans Memorial Bridge, workers can't use explosives for the new pillars closest to the old structure. Underwater explosives could undermine footings for the old bridge.
Pouring concrete 70 feet under water presents challenges. Manning said pressures at those depths "can float concrete." The trick, he said, is to pour a bunch of it.
"You can spend two or three months just doing a footing," Malone said. "It's a major effort."
Braden noted the existing bridge was built before Norris Dam created the lake, so those builders weren't faced with deep water issues.
The 1,915-
Wider and taller
Pouring concrete for the pillars will require occasional closing of one lane on Veterans Memorial Bridge, Malone said. Cement trucks will use the old bridge to pour concrete for pillars in the middle spans.
TDOT paid Britton Bridge $20,000 to reinforce the old bridge. It is listed as structurally
poor because of deterioration over the years. Although the reinforcement will allow
cement trucks to sit on it, the fixes were not sufficient to lift the weight limits.
Loaded commercial rigs over 35 tons now must use a 70-
Once the pillars are set for the new bridge, workers will connect the three spans
with metal I-
While the old bridge carried traffic on two, 11-
"If you have car trouble, you'll have a place to pull over. Also, there's mobile home manufacturers on either side of the river, so it'll make it easier for wide loads," Manning said.
The completed bridge, Manning said, will resemble other interstate bridges, with
a 32-
Drivers will be using the bridge months before the project is finished, Malone said. Workers will divert traffic onto the new bridge as they pave approaches of about 600 feet long on each end of the new bridge.
That's when drivers will notice they are traveling on a bridge that is roughly level with the top of the metal trusses of the old bridge.
The new bridge deck will be 50-
Once the new bridge and approaches are finished, workers will begin dismantling the old one. Manning said the water is too deep to use explosives to bring it down.
"Removal of the old bridge is going to be a task," he said. "Basically, they dismantle it piece by piece."